Project progress is tracked in the project plan, but details of that progress is captured in regular status reports. Use this template to document status of the project. A full collection of templates is available at TenStep Template Collective.
Kuhn & Associates
<TITLE>
PROJECT STATUS
Week ending <DATE>
To: |
<NAMES>
|
Prepared by: |
<NAME> |
Project Names: |
Intranet Design & Implementation
|
Key Accomplishments This Period
Planned Accomplishments Next Period
Outstanding tasks:
Outstanding Issues/Concerns:
(List all issues/concerns having an impact on the schedule and/or budget of the project.)
Key Concerns |
Yes |
No |
Risk of Scope Increase? |
|
X |
Risk of Missing Deliverable Dates? |
|
X |
Budget Increases or New Items? |
|
X |
Obstacles to Achieving Results? |
|
X |
Resource Problems? |
|
X |
Other Critical Issues? |
|
X |
Explanation and Impact of Questions marked "Yes":
<TITLE> Project Schedule Status:
Resource |
Planned (Base) Hours |
Actual Hours
Week |
Actual Hours to Date |
Planned Remaining Hours Estimated |
Revised Hours (Actual + Remaining) |
Variance (Base Hours - Revised Hours) |
Web Maintenance (<NAME>) |
0 |
36 |
298 |
0 |
0 |
0 |
Project Management - Intranet (<NAME>) |
250 |
24 |
156 |
0 |
250 |
0 |
Web Development (<NAME>) |
400 |
36 |
232 |
0 |
400 |
0 |
Content Management (<NAME>) |
400 |
12 |
330 |
0 |
400 |
0 |
TOTAL |
1050 |
108 |
1016 |
332 |
872 |
0 |
Variance Explanation:
Web Maintenance was added due to accelerated delivery of intranet site to coincide with Client Rollout <DATE>. Use of additional resources to meet the earlier deadline and postponement of training caused additional burden for web site maintenance before CLIENT staff assumes responsibilities. (<DATE>) |